Planning and Design
June 2024
-
Ajayan Bridge Replacement
- Status: Design Completed
- Estimated Construction Cost: TBD
- Contractor: NC Macario & Associates
- Estimated start of construction: FY2024
-
Aplacho Bridge Replacement
- Status: Design Completed
- Estimated Construction Cost: TBD
- Contractor: Duenas Camacho & Associates
- Estimated start of construction: FY2024
-
Route 10A, Phase 1 Reconstruction and Widening GIA/Tiyan Intersection
- Status: Design in Progress
- Estimated Construction Cost: $25M
- Contractor: Duenas Camacho & Associates
- Estimated start of construction: FY2024
-
Route 14B, Ypao Road, Phase 2
- Status: Design Completed
- Estimated Construction Cost: $12.6M
- Contractor: EM Chen & Associates
- Estimated start of construction: FY2025
-
Route 17, Phase 2B
- Status: Design Completed
- Estimated Construction Cost: $29.3M
- Contractor: Duenas, Camacho and Associates
- Estimated start of construction: FY2025
-
Route 20 (Tiyan Parkway), Phase 2
- Status: Design Completed
- Estimated Construction Cost: $31.4M
- Contractor: TG Engineers
- Estimated start of construction: FY2027
-
Route 14 Resurfacing (Route 1 to Archbishop Felixberto Flores Circle): Medians and Sidewalks
- Status: Design in Progress
- Estimated Construction Cost: $15M
- Contractor: GHD
- Estimated start of construction: FY2024
-
Route 20 (Tiyan Parkway) Structure Demolition, Phase 2
- Status: Planning
- Estimated Construction Cost: $750,000
- Contractor: TBD
- Estimated start of construction: FY2026
-
Route 1/8 Memorial
- Status: Planning
- Estimated Construction Cost: TBD
- Contractor: TBD
- Estimated start of construction: TBD
-
Route 10 Safety Improvements (Route 4 to Route 8/16)
- Status: Design Completed
- Estimated Construction Cost: $12.5M
- Contractor: WSP USA, Inc.
- Estimated start of construction: FY2024
-
Ylig Memorial
- Status: Design Completed
- Estimated Construction Cost: $500,000
- Contractor: PTG
- Estimated start of construction: FY2024
-
Route 1 Pavement Markings Restoration, Juan Jacinto Drive to Gayinero Road (Maintenance)
- Status: Planning in Progress
- Estimated Construction Cost: TBD
- Contractor: N/A
- Estimated start of construction: TBD
-
Route 8 Pavement Markings Restoration, Route 1 to Tri-Intersection (Maintenance)
- Status: Planning in Progress
- Estimated Construction Cost: $354,000
- Contractor: NA
- Estimated start of construction: TBD
-
Route 4 Pavement Markings Restoration, Route 1 to Pago Bay Bridge (Maintenance)
- Status: Planning in Progress
- Estimated Construction Cost: TBD
- Contractor: NA
- Estimated start of construction: TBD
-
Islandwide Raised Medians Painting, Route 1 (Route 8 to Macy’s Entrance), Route 16 (Route 1 to Tri-Intersection), Route 4 (Route 10 to Route 1), Route 8 (Route 1 to Tri-Intersection) Maintenance
- Status: Planning in Progress
- Estimated Construction Cost: $46,000
- Contractor: N/A
- Estimated start of construction: TBD
-
Islandwide Accessibility Accomodation and Drainage Improvements
- Status: Design Completed
- Estimated Construction Cost: $500,000
- Contractor: WSP USA, Inc.
- Estimated start of construction: FY2025
-
Leo Palace Bridge / Pago Bridge Scour Countermeasures
- Status: Planning in Progress
- Estimated Construction Cost: $4.6M
- Contractor: GHD
- Estimated start of construction: FY2026
-
Fonte Inland, Maina Culvert, & Merizo Inland Culvert Rehabilitation
- Status: Planning in Progress
- Estimated Construction Cost: $3.7M
- Contractor: SSFM
- Estimated start of construction: FY2027
-
Route 2, 4, and Route 4A Planning Study
- Status: Planning in Progress
- Estimated Construction Cost: N/A
- Contractor: WSP USA, Inc.
- Estimated start of construction: N/A
-
Route 1 Reconstuction of Multiple Bridges (Hagatna to Piti)
- Status: Design in Progress
- Estimated Construction Cost: $115.5M
- Contractor: GHD
- Estimated start of construction: FY2024
-
Under Pavement Infrastructure Retrofit
- Status: Design in Progress
- Estimated Construction Cost: $165.4M
- Contractor: GHD
- Estimated start of construction: FY2024
-
Ajayan Bridge Temporary Shoring
- Status: Design in Progress
- Estimated Construction Cost: TBD
- Contractor: EMPSCO
- Estimated start of construction: TBD
-
Islandwide Bridge Safety Improvements
- Status: Design in Progress
- Estimated Construction Cost: $1M
- Contractor: WSP USA, Inc.
- Estimated start of construction: FY2026
-
Route 1 Widening at Rt 26, Rt 27, Signal at Liguan Ave - Design
- Status: Planning
- Estimated Construction Cost: TBD
- Contractor: TBD
- Estimated start of construction: TBD
-
Route 28 from Route 3 to Bumuchachu Road
- Status: Planning
- Estimated Construction Cost: TBD
- Contractor: TBD
- Estimated start of construction: TBD
-
Route 10A Reconstruction and Widening, GIAA to Route 16, Phase 2
- Status: Design In Progress
- Estimated Construction Cost: TBD
- Contractor: DCA
- Estimated start of construction: TBD
-
Auto Lot Expansion and Shared Access Road Pavement
- Status: Design Completed
- Estimated Construction Cost: $705,000
- Contractor: WSP
- Estimated start of construction: FY2024
-
Islandwide Traffic Signal Repairs from Typhoon Mawar
- Status: Planning
- Estimated Construction Cost: $1.2M
- Contractor: TBD
- Estimated start of construction: FY2024
-
Islandwide Routed Road Signage Repairs from Typhoon Mawar Damage
- Status: Planning
- Estimated Construction Cost: $1.95M
- Contractor: TBD
- Estimated start of construction: FY2024
-
Route 1 Striping Repairs from Route 6 (Adelup to Alupang Towers from Typhoon Mawar Damage)
- Status: Planning
- Estimated Construction Cost: $350,000
- Contractor: TBD
- Estimated start of construction: FY2024
-
Guatali Bridge Retrofit
- Status: Planning
- Estimated Construction Cost: $15M
- Contractor: TBD
- Estimated start of construction: FY2025
-
Route 15 Widening from Route 10 to GPA/GWA Facility
- Status: Planning
- Estimated Construction Cost: $30M
- Contractor: TBD
- Estimated start of construction: FY2025
-
Traffic Signal System Upgrade, Phase 1
- Status: Planning
- Estimated Construction Cost: $1.5M
- Contractor: TBD
- Estimated start of construction: FY2025
-
Traffic Signal System Upgrade, Phase 2
- Status: Planning
- Estimated Construction Cost: $2M
- Contractor: TBD
- Estimated start of construction: FY2025
-
Route 29 Rehabilitation
- Status: Planning
- Estimated Construction Cost: $30M
- Contractor: TBD
- Estimated start of construction: FY2026
-
Route 27 Widening
- Status: Planning
- Estimated Construction Cost: $30M
- Contractor: TBD
- Estimated start of construction: FY2027
-
Route 6, Rehabilitation from Rt 1 Veteran Cemetery to Rt 1 Adelup
- Status: Planning
- Estimated Construction Cost: $25M
- Contractor: TBD
- Estimated start of construction: FY2026
-
Route 26 Widening
- Status: Planning
- Estimated Construction Cost: $17.6M
- Contractor: TBD
- Estimated start of construction: FY2026
-
Islandwide Safety Projects
- Status: Design In Progress
- Estimated Construction Cost: $7.5M
- Contractor: TBD
- Estimated start of construction: FY2024-FY2027
-
Islandwide Pavement Improvements (Pavement and Pavement Marking) (IDIQ): TO 2 Route 10
- Status: Design Completed
- Estimated Construction Cost: $1.4M
- Contractor: WSP
- Estimated start of construction: FY2024
-
Islandwide Pavement Improvements (Pavement and Pavement Marking) (IDIQ): TO3 Route 2A, 8, 14A, 30, 32
- Status: Design In Progress
- Estimated Construction Cost: $1.5M
- Contractor: WSP
- Estimated start of construction: FY2025
-
Islandwide Guardrail Repair and Replacement (IDIQ): TO 2 Route 10
- Status: Design Completed
- Estimated Construction Cost: $0.16M
- Contractor: WSP
- Estimated start of construction: FY2024
-
Islandwide Safety Improvements (Striping and Marking) (IDIQ): TO 1 Route 1, Route 11 to Route 6
- Status: Design In Progress
- Estimated Construction Cost: $1.5M
- Contractor: WSP
- Estimated start of construction: FY2024