Ongoing Projects
March 2026
- Route 14B Reconstruction and Widening (Route 14 to Carmen Memorial Dr) Phase 1 Cliffside
- Project Start: October 2022
- Scope: Reconstruction and Widening
- Cost: $11.17M
- Contractor: InfraTech International, LLC
- Est. Progress: 99% Complete
- Route 5 and Portion of Route 12, Reconstruction and Widening (Route 2A to Naval Magazine/Route 12)
- Project Start: September 2022
- Scope: Reconstruction and Widening
- Cost: $12.95M
- Contractor: InfraTech International, LLC
- Est. Progress: 99% Complete
- Islandwide Primary Roads Paving and Pavement Marking (IDIQ)
- Project Start: March 2025
- Scope: Paving and Marking
- Cost: $1.86M
- Contractor: Hawaiian Rock Products
- Est. Progress: 99% Complete
- Islandwide Safety Improvements on Primary Roads (Striping and Marking) - IDIQ 2
- Project Start: March 2025
- Scope: Striping and Marking
- Task Order No. 1 (Route 1 from Route 6 to Route 11)
- Cost: $1.17M
- Contractor: Hawaiian Rock Products
- Est. Progress: 99% Complete
- Replacement of Ylig Bridge (Ph 2) - Ylig Memorial
- Project Start: March 2025
- Scope: Memorial Vault and Parking
- Cost: $0.47M
- Contractor: Korando Corporation
- Est. Progress: 80% Complete
- Islandwide Safety Improvements on Primary Roads (Striping and Marking) - IDIQ 2
- Project Start: June 2025
- Scope: Striping and Marking
- Task Order No. 2 (Route 1 from Route 6 to Alupang Tower)
- Cost: $0.78M
- Contractor: Hawaiian Rock Products
- Est. Progress: 99% Complete
- Islandwide Primary Roads Paving and Pavement Marking (IDIQ)
- Project Start: July 2025
- Scope: Paving and Marking
- Task Order No. 4 (Route 10 Safety Improvements)
- Cost: $11M
- Contractor: Hawaiian Rock Products
- Est. Progress: 60% Complete