Completed Projects

March 2026

Federally funded

  • Route 14 Resurfacing from Route 1 to Route 14B
    • Contractor: Hawaiian Rock Products
    • Completed: May 2024
    • Final Cost: $13.5M
  • Islandwide Primary Roads Paving and Pavement Marking TO No. 2 Route 10 Pavement Repairs
    • Contractor: Hawaiian Rock Products
    • Completed: July 2024
    • Final Cost: $979,561
  • Guatali Route 2A, Temporary Restoration of Guatali Bridge & Embankment
    • Contractor: Chi Construction
    • Completed: November 2008
    • Final Cost: $189,704
  • Route 1 U-Turn Reconstruction (Tamuning)
    • Contractor: Maeda Pacific Corp.
    • Completed: February 2009
    • Final Cost: $137,690
  • 2009 Islandwide Bridge Inspections
    • Contractor: Parsons Brinckerhoff, Inc.
    • Completed: April 2009
    • Final Cost: N/A
  • Tinaga Bridge Permanent Restoration
    • Contractor: BME & Sons, Inc.
    • Completed: August 2009
    • Final Cost: $223,685
  • Route 15 (in front of DOC, Mangilao)
    • Contractor: Maeda Pacific Corp.
    • Completed: December 2009
    • Final Cost: $649,279
  • Guardrail Replacement Phase 1
    • Contractor: Orion Construction Corporation
    • Completed: February 2010
    • Final Cost: $4.54M
  • Skatepark Barrier/Iglesia Circle Traffic Signal
    • Contractor: Kinden Corp.
    • Completed: March 2010
    • Final Cost: $552,416
  • LED Signal Light Upgrade
    • Contractor: Kinden Corporation
    • Completed: March 2010
    • Final Cost: $521,875
  • GPS Lock and Loops
    • Contractor: Kinden Corporation
    • Completed: March 2010
    • Final Cost: $91,255
  • Pavement Markings Improvement Phase 1
    • Contractor: Nippo Construction
    • Completed: April 2010
    • Final Cost: $2.09M
  • Pavement Markings Improvement Phase 2
    • Contractor: Highway Safety Services
    • Completed: March 2010
    • Final Cost: $1.63M
  • Guardrail Replacement Phase 2
    • Contractor: Nippo Corporation
    • Completed: July 2010
    • Final Cost: $3.22M
  • Masso River Bridge Embankment
    • Contractor: Chi Construction
    • Completed: December 2011
    • Final Cost: $293,198
  • Islandwide & School Zone Signs
    • Contractor: Highway Safety Services
    • Completed: December 2011
    • Final Cost: $176,275
  • Route 2 Culverts & Slide Repair
    • Contractor: IMCO
    • Completed: May 2012
    • Final Cost: $3.8M
  • Route 15 Embankment Restoration
    • Contractor: International Bridge Corp.
    • Completed: March 2012
    • Final Cost: $488,566
  • Route 6A Murray Road, Embankment Restoration
    • Contractor: Rex International
    • Completed: July 2012
    • Final Cost: $302,047
  • Route 8/10/16 Tri Intersection
    • Contractor: Kinden Corporation
    • Completed: June 2012
    • Final Cost: $5.7M
  • Route 25 (Alageta Road)
    • Contractor: Guam Construction Co.
    • Completed: July 2012
    • Final Cost: $7.6M
  • Route 16/GMF Post Office/ Army National Guard Intersection Signal Upgrade
    • Contractor: Maeda Pacific Corp.
    • Completed: March 2012
    • Final Cost: $1.5M
  • North Guam Signalization
    • Contractor: Bejjess Enterprises Inc., GEMCCO
    • Completed: August 2012
    • Final Cost: $985,296
  • Rehabilitation of Route 4 Bridges (Talofofo & Togcha River)
    • Contractor: Black Construction
    • Completed: March 2012
    • Final Cost: $4.2M
  • Route 7A Resurfacing
    • Contractor: Sumitomo Mitsui Const. Co.
    • Completed: December 2012
    • Final Cost: $5.7M
  • Route 4 Resurfacing & Widening (McDonalds to Route 10)
    • Contractor: Hawaiian Rock Products
    • Completed: December 2012
    • Final Cost: $15M
  • Route 17 Rehabilitation & Widening
    • Contractor: Sumitomo Mitsui
    • Completed: February 2013
    • Final Cost: $6.5M
  • Route 11 Shore Protection
    • Contractor: Core Tech International
    • Completed: April 2013
    • Final Cost: $4.9M
  • Route 11 Improvements & Traffic Enforcement Screening Station
    • Contractor: Core Tech International
    • Completed: May 2013
    • Final Cost: $16.5M
  • Taleyfak Bridge Restoration
    • Contractor: Rex International
    • Completed: May 2013
    • Final Cost: $828,956
  • Route 4 Resurfacing & Widening (Ylig Bridge to Pago Bay)
    • Contractor: Nippo Corporation
    • Completed: June 2013
    • Final Cost: $3.8M
  • Ylig Bridge Replacement
    • Contractor: Smithbridge Guam, Inc.
    • Completed: September 2015
    • Final Cost: $7.6M
  • Asan & Aguada Bridges Rehabilitation
    • Contractor: Maeda Pacific Corporation
    • Completed: October 2014
    • Final Cost: $894,344
  • Route 4, Togcha to Ipan Beach Park
    • Contractor: Nippo Corporation
    • Completed: October 2014
    • Final Cost: $770,569
  • Route 4 Agfayan Bridge
    • Contractor: Black Construction
    • Completed: April 2015
    • Final Cost: $4.5M
  • 2014 Islandwide Bridge Inspections
    • Contractor: Parsons Brinckerhoff, Inc.
    • Completed: April 2015
    • Final Cost: N/A
  • Inarajan North Leg (As-Misa)
    • Contractor: IMCO
    • Completed: July 2015
    • Final Cost: $1.2M
  • Tiyan Parkway Phase 1
    • Contractor: IMCO
    • Completed: June 2015
    • Final Cost: $7.4M
  • Route 17 Rehabilitation & Widening Phase 2A
    • Contractor: Nippo Corporation
    • Completed: November 2015
    • Final Cost: $2.7M
  • Replacement of Welded Petroleum Distribution Piping & Appurtenances
    • Contractor: Rex International
    • Completed: November 2015
    • Final Cost: $1.5M
  • Route 1 Resurfacing (Yigo - Asan/Piti)
    • Contractor: Nippo Corporation
    • Completed: November 2015
    • Final Cost: $773,155
  • Route 25/26 Intersection Improvement
    • Contractor: Korando Corporation
    • Completed: August 2016
    • Final Cost: $2.9M
  • Route 1 Signalized Pedestrian Crossing at Chamorro Village
    • Contractor: Maeda Pacific
    • Completed: June 2016
    • Final Cost: $185,312
  • Route 1/8 Intersection Improvements and Agana Bridges Replacement (Design-Build)
    • Contractor: Core Tech International
    • Completed: August 2016
    • Final Cost: $15.8M
  • Route 20 Tiyan Parkway Structure Demolition, Phase 1
    • Contractor: Maeda Pacific
    • Completed: March 2018
    • Final Cost: $558,370
  • Bile/Pigua Bridge Replacements
    • Contractor: Korando Corporation
    • Completed: June 2018
    • Final Cost: $4.7M
  • 2017 Islandwide Bridge Inspections
    • Contractor: TG Engineers
    • Completed: December 2018
    • Final Cost: $1M
  • Route 5 Partial Road Repair
    • Contractor: Hawaiian Rock Products
    • Completed: November 2005
    • Final Cost: Funding: CCIV USN NAVFACMAR
  • Route 3A Pavement Restoration
    • Contractor: Hawaiian Rock Corporation
    • Completed: August 2019
    • Final Cost: $338,603
  • Route 1/3 Intersection Improvements
    • Contractor: Maeda Pacific Corp.
    • Completed: February 2020
    • Final Cost: $7.2M
  • Resurfacing: Route 1 (Asan - Piti and Yigo - Dededo); Route 8 (Barrigada and Mongmong Toto); Route 8/Canada-Toto Loop Road Intersection Improvements
    • Contractor: Hawaiian Rock Products
    • Completed: April 2020
    • Final Cost: $9.1M
  • Route 3 Widening from Route 28 to Chalan Kareta
    • Contractor: Black Construction Corp.
    • Completed: July 2020
    • Final Cost: $42.6M
  • Atantano Bridge (Temporary Repairs 2019)
    • Contractor: Korando Corp.
    • Completed: August 2021
    • Final Cost: $347,708.05
  • Route 1 Resurfacing from Route 30 to Route 10A
    • Contractor: Hawaiian Rock Products
    • Completed: August 2022
    • Final Cost: $8.6M
  • Route 28 Rehabiliation from Route 1 to Bumuchachu Road
    • Contractor: Hawaiian Rock Products
    • Completed: March 2023
    • Final Cost: $6.5M
  • Islandwide Signing System Upgrade
    • Contractor: Highway Safety Services
    • Completed: November 2022
    • Final Cost: $480,166.50
  • Islandwide Primary Roads Paving and Pavement Marking TO No.1 Route 4 Pavement Repairs North of Chalan Kinaka
    • Contractor: Hawaiian Rock Products
    • Completed: December 2022
    • Final Cost: $472,116.13
  • Islandwide Safety Improvements on Primary Roads (Striping and Marking) TO No. 1 Route 4 from Route 1 to Route 10
    • Contractor: Highway Safety Services
    • Completed: September 2022
    • Final Cost: $263,786.65
  • Islandwide Improvements on Primary Roads (Striping and Marking) TO No.2 Route 8 from Route 1/8/16 Tri-Intersection to Route 1/8 Intersection to Route 10
    • Contractor: Highway Safety Services
    • Completed: September 2023
    • Final Cost: $228,480.35
  • Islandwide Guardrail Repair and Replacement TO No. 1 Route 4 from Route 1 to Route 10
    • Contractor: Highway Safety Services
    • Completed: May 2024
    • Final Cost: $428,880.40