Ongoing Projects

August 2026

  • Route 14B Reconstruction and Widening (Route 14 to Carmen Memorial Dr) Phase 1 Cliffside
    • Project Start: October 2022
    • Scope: Reconstruction and Widening
    • Cost: $11.17M
    • Contractor: InfraTech International, LLC
    • Est. Progress: 99% Complete
  • Route 5 and Portion of Route 12, Reconstruction and Widening (Route 2A to Naval Magazine/Route 12)
    • Project Start: September 2022
    • Scope: Reconstruction and Widening
    • Cost: $12.95M
    • Contractor: InfraTech International, LLC
    • Est. Progress: 99% Complete
  • Islandwide Primary Roads Paving and Pavement Marking (IDIQ)
    • Project Start: March 2025
    • Scope: Paving and Marking
    • Cost: $1.86M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 99% Complete
  • Islandwide Safety Improvements on Primary Roads (Striping and Marking) - IDIQ 2
    • Project Start: March 2025
    • Scope: Striping and Marking
    • Task Order No. 1 (Route 1 from Route 6 to Route 11)
    • Cost: $1.17M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 99% Complete
  • Replacement of Ylig Bridge (Ph 2) - Ylig Memorial
    • Project Start: March 2025
    • Scope: Memorial Vault and Parking
    • Cost: $0.47M
    • Contractor: Korando Corporation
    • Est. Progress: 99% Complete
  • Islandwide Safety Improvements on Primary Roads (Striping and Marking) - IDIQ 2
    • Project Start: June 2025
    • Scope: Striping and Marking
    • Task Order No. 2 (Route 1 from Route 6 to Alupang Tower)
    • Cost: $0.78M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 99% Complete
  • Islandwide Primary Roads Paving and Pavement Marking (IDIQ)
    • Project Start: July 2025
    • Scope: Paving and Marking
    • Task Order No. 4 (Route 10 Safety Improvements)
    • Cost: $11M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 83% Complete
  • Islandwide Safety Improvements (Striping and Marking) - IDIQ 2
    • Project Start: April 2026
    • Scope: Striping and Marking
    • Task Order No. 3 (Route 1 from Route 27 - AAFB)
    • Cost: $2.03M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 38% Complete
  • Islandwide Traffic Signal Repairs from Typhoon Mawar
    • Project Start: April 2026
    • Scope: Signal Repairs
    • Cost: $1.34M
    • Contractor: Polyphase Systems, Inc.
    • Est. Progress: 0% Complete
  • Islandwide Accessibility Accommodation and Drainage Improvements
    • Project Start: May 2026
    • Scope: ADA and Drainage Improvements
    • Cost: $1.32M
    • Contractor: Mega United Corporation
    • Est. Progress: 0% Complete
  • Islandwide Primary Roads Paving and Pavement Marking (IDIQ)
    • Project Start: July 2025
    • Scope: Paving and Marking
    • Task Order No. 5 (Route 17)
    • Cost: $9.75M
    • Contractor: Hawaiian Rock Products
    • Est. Progress: 4% Complete