Territorial Transportation Improvement Plan Projects - Construction
February 6, 2012 - Ongoing Projects
1 North Guam Signalization
Project Start: August 2009
Completion: May 2012
Scope: Traffic Signalization & Wusstig Right Turn Lane
Cost: $1.06M
Contractor: Bejjess Enterprises Inc., GEMCCO
Est. Progress: 80%
2 Masso River Bridge Embankment
Project Start: May 2010
Completion: December 2011
Scope: Embankment restoration
Cost: $330,000
Contractor: Chi Construction
Est. Progress: 100%
3 Route 25 (Alageta Road)
Reconstruction & Widening
Project Start: May 2010
Completion: March 2012
Scope: Reconstruction & Widening
Cost: $7.4M
Contractor: Guam Construction Company, Inc.
Est. Progress: 90%
4 Route 11 Shore Protection
Project Start: January 2010
Completion: May 2012
Scope: Seawall Protection –
Construction of rock revetment.
Cost: $5.1M
Contractor: Core Tech International
Est. Progress: 90%
Route 11 Improvements and Traffic
Enforcement Screening Station
Project Start: September 2011
Completion: September 2012
Scope: Road improvements and
Constructing Screening Station
Cost: $15.4M
Contractor: Core-Tech International
Est. Progress: 4%
5 Route 15 Embankment Restoration
(Near Ton Robit)
Project Start: March 2010
Completion: March 2012
Scope: Road Embankment Restoration
Cost: $943,000
Contractor: International Bridge Group
Est. Progress: 75%
6 Route 2 Culverts and Slide Repair
Project Start: June 2011
Completion: February 2012
Scope: Culvert Replacements
& Slide Repair
Cost: $3.8M
Contractor: IMCO
Est. Progress: 95%
7 Route 16/GMF Post Office/Army National
Guard Intersection Traffic Signal Upgrade
Project Start: January 2010
Completion: February 2012
Scope: Traffic Signal Upgrade
Cost: $1.5M
Contractor: Maeda Pacific Corporation
Est. Progress: 90%
8 Route 8/10/16 Tri Intersection Improvements
Project Start: March 2010
Completion: February 2012
Scope: Resurfacing, Widening & Signal Light Upgrade
Cost: $5.1M
Contractor: Kinden Corporation
Est. Progress: 84%
9 Route 4 Resurfacing (McDonalds to Route 10)
Project Start: August 2010
Completion: March 2012
Scope: Pavement Widening & Resurfacing
Cost: $16.4M
Contractor: Hawaiian Rock Products
Est. Progress: 90%
10 Route 4 Resurfacing & Widening (Ylig Bridge - Pago Bay)
Project Start: September 2010
Completion: June 2012
Scope: Pavement Resurfacing & Widening
Cost: $5.75M
Contractor: Nippo Corporation
Est. Progress: 35%
11 Route 17 Rehabilitation and Widening
Project Start: November 2010
Completion: June 2012
Scope: Reconstruction & Widening
Cost: $5.6M
Contractor: Sumitomo Mitsui Const. Co.
Est. Progress: 60%
12 Ylig Bridge Replacement
Project Start: November 2010
Completion: October 2012
Scope: Bridge Replacement
Cost: $8.0M
Contractor: Smithbridge Guam, Inc.
Est. Progress: 30%
13 Island-wide and School Zone Signs
Project Start: May 2010
Completion: December 2011
Scope: Traffic sign installation
Cost: $259,000
Contractor: Highway Safety Services
14 Route 7A Resurfacing
Project Start: September 2011
Completion: October 2012
Scope: Pavement Resurfacing
Cost: $4.7M
Contractor: Sumitomo Mitsui Construction Co.
Est. Progress: 30%
15 Route 6A Murray Road, Maina-Nimitz Hill
Project Start: January 2011
Completion: February 2012
Scope: Embankment Restoration
Cost: $312,275
Contractor: Rex International
Est. Progress: 80%
16 Route 11 Improvements and Traffic Enforcement Screening Station
Project Start: September 2011
Completion: September 2012
Scope: Road improvements and
Constructing Screening Station
Cost: $15.4M
Contractor: Core-Tech International
Est. Progress: 70%
17 Rehabilitation of Route 4 Bridges over the Talofofo & Togcha Rivers
Project Start: December 2010
Completion: June 2012
Scope: Bridge Rehabilitation
Cost: $3.39M
Contractor: Black Construction
Est. Progress: 65%
17 Route 1/8 Intersection Improvements and Agana Bridge Replacement
Project Start: September 2011
Completion: December 2013
Scope: Road improvements and Bridges
Replacement
Cost: $16.4M
Contractor: Core-Tech International
Est. Progress: 2%
Future Projects
18 Taleyfak Bridge Restoration
Expected Project Start: February 2012
Expected Completion: November 2012
Scope: Bridge Restoration
Cost: $793,411
Contractor: Rex International

Can't read the documents? Download Adobe Reader
