Construction Projects
April 20, 2013
1 Route 11 Improvements and Traffic Enforcement
Screening Station
Project Start: September 2011 Completion: June 2013
Scope: Road improvements and Constructing Weigh Station
Cost: $17.1M
Contractor: Core Tech International
Est. Progress: 95%
2 Route 11 Shore Protection
Project Start: January 2010 Completion: April 2013
Scope: Seawall Protection. Construction of rock revetment.
Cost: $5.2M
Contractor: Core Tech International
Est. Progress: 95%
3 Route 4 Resurfacing & Widening (Ylig Bridge to
Pago Bay)
Project Start: September 2010
Completion: March 2013
Scope: Pavement Widening, Resurfacing & Draining Improvements
Cost: $5.8M
Contractor: Nippo Corporation
Est. Progress: 95%
4 Ylig Bridge Replacement
Project Start: November 2010
Completion: July 2013
Scope: Bridge Replacement
Cost: $8.0M
Contractor: Smithbridge Guam, Inc.
Est. Progress: 75%
5 Route 1/8 Intersection Improvements and Agana Bridge
Replacement (Design Build)
Project Start: September 2011
Completion: May 2014
Scope: Road improvements and Bridges Replacement
Cost: $16.4M
Contractor: Core Tech International
Est. Progress: 40%
6 Taleyfak Bridge Restoration
Project Start: March 2012
Completion: April 2013
Scope: Bridge Restoration
Cost: $.9M
Contractor: Rex International
Est. Progress: 90%

Can't read the documents? Download Adobe Reader
