Completed Projects

March 2019

FHWA funded:

1 Guatali Route 2A, Temporary Restoration
of Guatali Bridge & Embankment

Contractor: Chi Construction
Completed: November 2008
Final Cost: $187,704

2 Route 1 U-Turn Reconstruction (Tamuning)

Contractor: Maeda Pacific Corp.
Completed: February 2009
Final Cost: $137,690

3 Tinaga Bridge Permanent Restoration

Contractor: BME & Sons, Inc.
Completed: August 2009
Final Cost: $223,685

4 Route 15 (in front of DOC, Mangilao)

Contractor: Maeda Pacific Corp.
Completed: December 2009
Final Cost: $649,279

5 Skatepark Barrier/Iglesia Circle Traffic Signal

Contractor: Kinden Corp.
Completed: March 2010
Final Cost: $562,923

6 Masso River Bridge Embankment

Contractor: Chi Construction
Completed: December 2011 Final
Cost: $330,000

7 Route 15 Embankment Restoration

Contractor: International Bridge Corp.
Completed: March 2012
Final Cost: $650,000

8 Route 15 Embankment Restoration

Contractor: IMCO
Completed: February 2012
Final Cost: $3.8M

9 Route 6A Murray Road, Maina-Nimitz Hill

Contractor: Rex International Completed: April 2012 Final Cost: $360,000

10 North Guam Signalization

Contractor: Bejjess Enterprises Inc., GEMCCO Completed: August 2012 Final Cost: $1.1 M

11 Route 25 (Alageta Road)

Contractor: Guam Construction Co. Completed: July 2012 Final Cost: $7.4M

12 Route 16/GMF Post Office/ Army National Guard Intersection Signal Upgrade

Contractor: Maeda Pacific Corp. Completed: July 2012 Final Cost: $1.5M

13 Route 8/10/16 Tri Intersection

Contractor: Kinden Corporation Completed: June 2012 Final Cost: $5.1M

14 Rehabilitation of Route 4 Bridges (Talofofo & Togcha River)

Contractor: Black Construction Completed: August 2012 Final Cost: $4.0M

15 Route 7A Resurfacing

Contractor: Sumitomo Mitsui Const. Co. Completed: December 2012 Final Cost: $5.5M

16 Route 4 Resurfacing & Widening (McDonalds to Route 10)

Contractor: Hawaiian Rock Products Completed: December 2012 Final Cost: $16.6M

17 Route 17 Rehabilitation & Widening

Contractor: Sumitomo Mitsui Completed: February 2013 Final Cost: $6M

18 Route 11 Improvements & Traffic Enforcement Screening
Station

Contractor: Core Tech International Completed: May 2013 Final Cost: $16.5M

19 Route 11 Shore Protection

Contractor: Core Tech International Completed: April 2013 Final Cost: $5.2M

20 Taleyfak Bridge Restoration

Completed: May 2013 Contractor: Rex International Final Cost: $.9M

21 Route 4 Resurfacing & Widening (Ylig Bridge to Pago Bay)

Contractor: Nippo Corporation Completed: June 2013 Final Cost: $3.8M

22 Ylig Bridge Replacement

Contractor: Smithbridge Guam, Inc. Completed: May 2014 Cost: $8.1M

23 Asan & Aguada Bridges Rehabilitation

Contractor: Maeda Pacific Corporation Completed: October 2014 Final Cost: $880,000

24 Route 4, Togcha to Ipan Beach Park

Contractor: Nippo Corporation Completed: October 2014 Final Cost: $835,000

25 Route 4 Agfayan Bridge

Contractor: Black Construction Completed: April 2015 Final Cost: $4.5M

26 Inarajan North Leg (As-Misa)

Contractor: IMCO Completed: June 2015 Final Cost: $1.2M

27 Route 20, Maga Haga Highway

Contractor: IMCO Completed: June 2015 Final Cost: $7.4M

28 Route 17 Rehabilitation & Widening , Phase 2A

Contractor: Nippo Corporation Completed: November 2015 Final Cost: $2.7M

29 Replacement of Welded Petroleum Distribution Piping & Appurtenances

Contractor: Rex International Completed: November 2015 Cost: $1.5 M

30 Route 1 Resurfacing (Yigo – Asan/Piti)

Contractor: Nippo Corporation Completed: November 2015 Final Cost: $773,155

31 Route 25/26 Intersection Improvement

Contractor: Korando Corporation Completed: June 2016 Final Cost: $2.9M

32 Route 1 Signalized Pedestrian Crossing at Chamorro
Village

Contractor: Maeda Pacific Completed: June 2016 Final Cost: $201,400

33 Route 27 (Hamburger Road) Pavement Rehabilitation (Maintenance)

Contractor: Maeda Pacific Completed: June 2016 Final Cost: $201,400

34 Route 26 Pavement Rehabilitation (Maintenance) (Maintenance)

Contractor: DPW & Hawaiian Rock Products Completed: August 2017 Final Cost: $288,854

35 Route 4 (Umatac) Pavement Rehabilitation (Maintenance) (Maintenance)

Contractor: DPW & Hawaiian Rock Products Completed: November 2017 Final Cost: $601,655

36 Route 4 Spot Repair Work (Maintenance)

Contractor: DPW & Hawaiian Rock Products Completed: April 2016 Final Cost: $82,542

37 Sgt. Roy T. Damian Road Spot Repair Work (Maintenance)

Contractor: DPW & Hawaiian Rock Products Completed: December 2015 Final Cost: $89,039

38 Resurfacing of Chalan Lumasu
(Chalan Guagua to Route 3), (Maintenance)

Contractor: Hawaiian Rock Products Completed: October 2015 Final Cost: $186,935

39 Chalan Balako Resurfacing (Maintenance)

Contractor: DPW & Hawaiian Rock Products Completed: March 2017 Final Cost: $201,139

40 Flood Mitigation of Lot 6-1, Block 2,
Barrigada, Route 8, Design-Build (Maintenance)

Contractor: ProPacific Builder Corporation Completed: January 2018 Final Cost: $108,985

41 Route 16 Pavement Markings Restoration
(Route 1 to Tri-Intersection), (Maintenance)

Contractor: DPW – HMC Completed: February 2018 Final Cost: $34,450

42 Route 3 Pavement Markings Restoration,
GRMC to Y-Sengsong, (Maintenance)

Contractor: DPW – HMC Completed: December 2017 Final Cost: $19,650

43 Gill Baza Access Road, Paving & Markings (Maintenance)

Contractor: NIPPO Completed: July 2012 Final Cost: $210,202

44 Bile/Pigua Bridge Replacements

Project Start: March 2016 Completion: June 2018 Scope: Replace Two Bridges Cost: $3.7 M Contractor: Korando Corporation

45 Route 20 Tiyan Parkway Structure Demolition, Phase 1

Project Start: October 2017 Completion: March 2018 Scope: Demolish five buildings Cost: $0.6M Contractor: Maeda Pacific

46 2009 Islandwide Bridge Inspections

Contractor: Parsons Brinckerhoff, Inc. Completed: April 2009 Final Cost: N/A

Local Funded:

47 Route 20 Tiyan Parkway Structure Demolition, Phase 1

Contractor: Orion Construction Corporation Completed: February 2010 Final Cost: $4.54M

48 LED Signal Light Upgrade

Contractor: Kinden Corporation Completed: March 2010 Final Cost: $521,875

49 GPS Lock and Loops

Contractor: Kinden Corporation Completed: March 2010 Final Cost: $91,255

50 Pavement Markings Improvement Phase 1

Contractor: Nippo Construction Completed: April 2010 Final Cost: $2.09M

51 Pavement Markings Improvement Phase 2

Contractor: Highway Safety Services Completed: March 2010 Final Cost: $1.63M

52 Guardrail Replacement Phase 2

Contractor: Nippo Corporation Completed: July 2010 Final Cost: $3.22M

53 Islandwide & School Zone Signs

Contractor: Highway Safety Services Completed: December 2011 Final Cost: $300,000

54 2014 Islandwide Bridge Inspections

Contractor: Parsons Brinckerhoff, Inc. Completed: April 2015 Final Cost: N/A

 

Can't read the documents? Download Adobe Reader

 

Back to top

Questions? Concerns?

Email us at helpdesk(gtp)guamtransportationprogram.com and you shall receive a response within 24 hours via email.

Join Our Mailing List

Register for updates on current and future contracting opportunities with the Government of Guam Department of Public Works.