Completed Projects
October 2020
Federally funded:
1
Guatali Route 2A, Temporary Restoration
of Guatali Bridge & Embankment
Contractor: Chi Construction
Completed: November 2008
Final Cost: $187,704
2 Route 1 U-Turn Reconstruction (Tamuning)
Contractor: Maeda Pacific Corp.
Completed: February 2009
Final Cost: $137,690
3 2009 Islandwide Bridge Inspections
Contractor: Parsons Brinckerhoff, Inc.
Completed: April 2009
Final Cost: N/A
4 Tinaga Bridge Permanent Restoration
Contractor: BME & Sons, Inc.
Completed: August 2009
Final Cost: $223,685
5 Route 15 (in front of DOC, Mangilao)
Contractor: Maeda Pacific Corp.
Completed: December 2009
Final Cost: $649,279
6 Guardrail Replacement Phase 1
Contractor: Orion Construction Corporation
Completed: February 2010
Final Cost: $4.54M
7 Skatepark Barrier/Iglesia Circle Traffic Signal
Contractor: Kinden Corp.
Completed: March 2010
Final Cost: $562,923
8 LED Signal Light Upgrade
Contractor: Kinden Corporation
Completed: March 2010
Final Cost: $521,875
9 GPS Lock and Loops
Contractor: Kinden Corporation Completed: March 2010 Final Cost: $91,255
10 Pavement Markings Improvement Phase 1
Contractor: Nippo Construction Completed: April 2010 Final Cost: $2.09M
11 Pavement Markings Improvement Phase 2
Contractor: Highway Safety Services Completed: March 2010 Final Cost: $1.63M
12 Guardrail Replacement Phase 2
Contractor: Nippo Corporation Completed: July 2010 Final Cost: $3.22M
13 Masso River Bridge Embankment
Contractor: Chi Construction
Completed: December 2011 Final
Cost: $330,000
14 Islandwide & School Zone Signs
Contractor: Highway Safety Services Completed: December 2011 Final Cost: $300,000
15 Route 2 Culverts & Slide Repair
Contractor: IMCO Completed: February 2012 Final Cost: $3.8M
16 Route 15 Embankment Restoration
Contractor: International Bridge Corp.
Completed: March 2012
Final Cost: $650,000
17 Route 6A Murray Road, Maina-Nimitz Hill
Contractor: Rex International Completed: April 2012 Final Cost: $360,000
18 Route 8/10/16 Tri Intersection
Contractor: Kinden Corporation Completed: June 2012 Final Cost: $5.1M
19 Route 25 (Alageta Road)
Contractor: Guam Construction Co. Completed: July 2012 Final Cost: $7.4M
20 Route 16/GMF Post Office/ Army National Guard Intersection Signal Upgrade
Contractor: Maeda Pacific Corp. Completed: July 2012 Final Cost: $1.5M
21 North Guam Signalization
Contractor: Bejjess Enterprises Inc., GEMCCO Completed: August 2012 Final Cost: $1.1 M
22 Rehabilitation of Route 4 Bridges (Talofofo & Togcha River)
Contractor: Black Construction Completed: August 2012 Final Cost: $4.0M
23 Route 7A Resurfacing
Contractor: Sumitomo Mitsui Const. Co. Completed: December 2012 Final Cost: $5.5M
24 Route 4 Resurfacing & Widening (McDonalds to Route 10)
Contractor: Hawaiian Rock Products Completed: December 2012 Final Cost: $16.6M
25 Route 17 Rehabilitation & Widening
Contractor: Sumitomo Mitsui Completed: February 2013 Final Cost: $6M
26 Route 11 Shore Protection
Contractor: Core Tech International Completed: April 2013 Final Cost: $5.2M
27
Route 11 Improvements & Traffic Enforcement Screening
Station
Contractor: Core Tech International Completed: May 2013 Final Cost: $16.5M
28 Taleyfak Bridge Restoration
Completed: May 2013 Contractor: Rex International Final Cost: $.9M
29 Route 4 Resurfacing & Widening (Ylig Bridge to Pago Bay)
Contractor: Nippo Corporation Completed: June 2013 Final Cost: $3.8M
30 Ylig Bridge Replacement
Contractor: Smithbridge Guam, Inc. Completed: May 2014 Cost: $8.1M
31 Asan & Aguada Bridges Rehabilitation
Contractor: Maeda Pacific Corporation Completed: October 2014 Final Cost: $880,000
32 Route 4, Togcha to Ipan Beach Park
Contractor: Nippo Corporation Completed: October 2014 Final Cost: $835,000
33 Route 4 Agfayan Bridge
Contractor: Black Construction Completed: April 2015 Final Cost: $4.5M
34 2014 Islandwide Bridge Inspections
Contractor: Parsons Brinckerhoff, Inc. Completed: April 2015 Final Cost: N/A
35 Inarajan North Leg (As-Misa)
Contractor: IMCO Completed: June 2015 Final Cost: $1.2M
36 Route 20, Maga Haga Highway
Contractor: IMCO Completed: June 2015 Final Cost: $7.4M
37 Route 17 Rehabilitation & Widening , Phase 2A
Contractor: Nippo Corporation Completed: November 2015 Final Cost: $2.7M
38 Replacement of Welded Petroleum Distribution Piping & Appurtenances
Contractor: Rex International Completed: November 2015 Cost: $1.5 M
39 Route 1 Resurfacing (Yigo – Asan/Piti)
Contractor: Nippo Corporation Completed: November 2015 Final Cost: $773,155
40 Route 25/26 Intersection Improvement
Contractor: Korando Corporation Completed: June 2016 Final Cost: $2.9M
41
Route 1 Signalized Pedestrian Crossing at Chamorro
Village
Contractor: Maeda Pacific Completed: June 2016 Final Cost: $201,400
42
Route 1/8 Intersection Improvements and
Agana Bridges Replacement
(Design-Build)
Completion: August 2016 Scope: Intersection Improvements & Replace 2 bridges Cost: $15.8M Contractor: Core Tech International
43 Route 20 Tiyan Parkway Structure Demolition, Phase 1
Completion: March 2018 Scope: Demolish five buildings Cost: $0.6M Contractor: Maeda Pacific
44 Bile/Pigua Bridge Replacements
Completion: June 2018 Scope: Replace Two Bridges Cost: $3.7 M Contractor: Korando Corporation
45 2017 Islandwide Bridge Inspections
Completion: December 2018 Scope: Inspection of bridges Cost: $850,000 Contractor: TG Engineers
46 Route 5 Partial Road Repair
Contractor: Hawaiian Rock Products Completed: November 2005 Funding: CCIV USN NAVFACMAR
47 EDI HUD Grant Project
Contractor:In-House (HMC) Completed: September 2015 Final Cost: $245,000.00
48 Route 3A Pavement Restoration
Contractor: Hawaiian Rock Corporation Completed: August 2019 Final Cost: $0.7M
49 Route 1/3 Intersection Improvements
Contractor: Maeda Pacific Corp. Completed: February 2020 Final Cost: $7.2M
50
Resurfacing: Route 1 (Asan - Piti and Yigo - Dededo);
Route 8 (Barrigada and Mongmong Toto);
Route 8/Canada-Toto Loop Road
Intersection Improvements
Contractor: Hawaiian Rock Products Completed: April 2020 Final Cost: $9.1M
51 Route 3 Widening from Route 28 to Chalan Kareta
Contractor: Black Construction Corp. Completed: July 2020 Final Cost: $42.6M

Locally funded:
1 Route 27 (Hamburger Road) Pavement Rehabilitation (Maintenance)
Contractor: Maeda Pacific Completed: June 2016 Final Cost: $201,400
2 Route 26 Pavement Rehabilitation (Maintenance)
Contractor: DPW & Hawaiian Rock Products Completed: August 2017 Final Cost: $288,854
3 Route 4 (Umatac) Pavement Rehabilitation (Maintenance)
Contractor: DPW & Hawaiian Rock Products Completed: November 2017 Final Cost: $601,655
4 Route 4 Spot Repair Work (Maintenance)
Contractor: DPW & Hawaiian Rock Products Completed: April 2016 Final Cost: $82,542
5 Sgt. Roy T. Damian Road Spot Repair Work (Maintenance)
Contractor: DPW & Hawaiian Rock Products Completed: December 2015 Final Cost: $89,039
6
Resurfacing of Chalan Lumasu
(Chalan Guagua to Route 3), (Maintenance)
Contractor: Hawaiian Rock Products Completed: October 2015 Final Cost: $186,935
7 Chalan Balako Resurfacing (Maintenance)
Contractor: DPW & Hawaiian Rock Products Completed: March 2017 Final Cost: $201,139
8
Flood Mitigation of Lot 6-1, Block 2,
Barrigada, Route 8, Design-Build (Maintenance)
Contractor: ProPacific Builder Corporation Completed: January 2018 Final Cost: $108,985
9
Route 16 Pavement Markings Restoration
(Route 1 to Tri-Intersection), (Maintenance)
Contractor: DPW – HMC Completed: February 2018 Final Cost: $34,450
10
Route 3 Pavement Markings Restoration,
GRMC to Y-Sengsong, (Maintenance)
Contractor: DPW – HMC Completed: December 2017 Final Cost: $19,650
11 Gill Baza Access Road, Paving & Markings (Maintenance)
Contractor: NIPPO Completed: July 2012 Final Cost: $210,202
12 Barrigada Village Road Spot Repair Work (Maintenance)
Contractor: IBC Marianas, Inc. Completed: January 2012 Final Cost: $181,849.00
13 Route 4 As-Alonzo Spot Repair Work (Maintenance)
Contractor: Hawaiian Rock Products Completed: August 2017 Final Cost: $12,000.00
14
Repair Of Damaged Pavement Section At
Various Locations (Maintenance)
Contractor: Hawaiian Rock Products Completed: December 2015 Final Cost: $302,300.00
15 Islandwide Pavement Resurfacing, Rounds 1 & 2. (Maintenance)
Contractor: Hawaiian Rock Products Completed: July 2019 Final Cost: $3,200,000.00
16
Maintenance Services For The Marianas Terrace
Ponding Basin
Contractor: UMS Equipment Rental, Inc. Completed: January 2020 Final Cost: $300,000
17
Route 1 Pavement Marking Improvements,
East Agana to Route 16 (Maintenance)
Contractor: DPW and Hawaiian Rock Products Completed: June 2018 Final Cost: $30,950

Can't read the documents? Download Adobe Reader